Road closures and delays

Road closures
St.Helier - Union Street eastbound closed between The Parade and Hue Street

Start date: Wednesday, 27/03/24
End date: Monday, 06/05/24
Traffic details: Road Closure     All Day
Promoter: Dandara Jersey Ltd
Contractor: Pallot Tarmac
Description: Eastbound road closure for footway improvement works near Government HQ. Traffic diverted via Cannon Street and Lemprilre Street, expect delays, especially at peak times.



Le Mont de Gouray will be closed from the Gorey Village Main Road to the junction with Le Mont Gabard

Start date: Saturday, 16/03/24
End date: Friday, 17/05/24
Traffic details: Road Closure     All Day
Promoter: Jersey Electricity
Contractor: Geomarine
Description: Le Mont de Gouray is closed for essential JEC sub station works. Diversion routes are posted. Businesses open as usual.



Emergency Activity - St.Helier - Kensington Place between Cheapside and Kensington Street

Start date: Tuesday, 23/04/24
End date: Wednesday, 24/04/24
Traffic details: Road Closure     All Day
Promoter: Jersey Water
Contractor: Jayen
Description: Burst water main on Kensington Place between Cheapside and Kensington Street. A lane closure is in place on the Esplanade to isolate the supply.



Delays
St.Helier La Route de St Aubin between Tyneville Lane and West Park Avenue.

Start date: Monday, 05/02/24
End date: Friday, 10/05/24
Traffic details: Portable Signals     All Day
Promoter: GoJ Drainage Capital Works
Contractor: Brenwal
Description: Traffic signals in place for West park sewer separation works. Expect delays, especially at peak times.



St.Helier - Trinity Hill Between Le Vier Mont to La Vallee des Vaux

Start date: Thursday, 18/04/24
End date: Friday, 24/05/24
Traffic details: Portable Signals     All Day
Promoter: GoJ Drainage Maintenance and Callouts
Contractor: Geomarine
Description: Temporary Traffic Signals for Emergency stabilisation works and pavement works.



St.Helier - La Motte Street improvements

Start date: Monday, 12/06/23
End date: Friday, 31/05/24
Traffic details: Lanes Reduced     All Day
Promoter: GoJ Traffic and Transport
Contractor: GoJ Traffic and Transport
Description: There is a 6 foot 6 inch width restriction in place on La Motte St. HGVs Diverted via Don Road while works are being undertaken.



Starting - next 5 days
Road closures
No future road closures at present
Delays
Emergency Activity - St.Saviour - Bagot Road - GHA

Start date: Wednesday, 24/04/24
End date: Wednesday, 24/04/24
Traffic details: Stop/Go (1 Man)     Between AM and PM Peaks
Promoter: Newtel
Contractor: Jsy Rd Driveway Repairs
Description: Locate and repair damaged fiber cable