St.Peter - La Grande Route de St Pierre - Between La Route du Manoir and La Rue du Vieux Presbytère

Start date: Friday, 31/07/26
End date: Wednesday, 26/08/26
Traffic details: Road Closure     All Day
Promoter: GoJ Drainage Capital Works
Contractor: Brenwal
Description: Road closed to finalise drainage connections that could not be done before due to existing main levels. Diversion routes posted



Moon Light Parade

Start date: Saturday, 15/08/26
End date: Sunday, 16/08/26
Traffic details: Road Closure     All Day
Promoter: The Jersey Battle of Flowers (Events) Limited
Contractor: N/A
Description: Moon Light Parade: Victoria Avenue and its approach roads will be closed between Bel Royal and West Park from 5:30pm until 1am on Sunday



St.Saviour - Bagatelle Road - Between Le Clos de Malershe and Patier Road.

Start date: Monday, 20/07/26
End date: Friday, 21/08/26
Traffic details: Road Closure     All Day
Promoter: GoJ Road Patching
Contractor: Pallot Tarmac
Description: Resurfacing of Bagatelle Road and a small section at the bottom of Mont Millais. More information about the scheme can be found at www.gov.je/travel/roads. Diversion routes posted.



Trinity - La Grande Route de St Jean - between La Rue du Becquet Vincent and La Rue des Houguettes

Start date: Saturday, 24/01/26
End date: Saturday, 17/10/26
Traffic details: Road Closure     All Day
Promoter: GoJ Drainage Capital Works
Contractor: Techno Groundworks
Description: Road closed for the northern Sewer Network Upgrades project - area 8. Diversion routes posted.



St.Helier - St Saviour`s Road - Between Brooklyn Street and Pleasant Street

Start date: Saturday, 18/07/26
End date: Saturday, 05/09/26
Traffic details: Road Closure     All Day
Promoter: Jersey Electricity
Contractor: Geomarine
Description: Road closed for excavation works to overlay Low voltage cables and complete service transfers prior to resurfacing in 2027. Diversion routes and one-way systems signposted.



Delays
St.Clement - La Greve d`Azette - Between Plat Douet Road and Green Road.

Start date: Monday, 27/07/26
End date: Friday, 21/08/26
Traffic details: Portable Signals     All Day
Promoter: Ashbe Construction
Contractor: Ashbe Construction
Description: Temporary traffic lights will be in operation to allow for Granite cladding works to boundary wall of Property Ceol na Mara.



Starting - next 7 days
Road closures
Gorey Fete Committee - Summer Fete

Start date: Friday, 21/08/26
End date: Friday, 21/08/26
Traffic details: Road Closure     All Day
Promoter: Gorey Fete Comittee
Contractor: N/A
Description: Le Mont de Gouray and La Route de la Côte will be made one way to down hill traffic (westbound) with uphill (eastbound) traffic diverted via Gorey Village from midday on Thursday 14th August. On Friday 16th August until midday on Saturday 17th August a full road closure in place.



Delays
No future delays at present